2022-01-14: Hardware order
Meeting Information
| Subject: | Milestone Meeting: Hardware order |
| Date/Time: | 14.01.2022, 10:00-10:20 |
| Location: | MS Teams |
| Note Taker: | Stefan Lüthi |
Participants
- Stefan Lüthi (maintainer)
- Roger Weber (advisor)
Agenda
- Milestone: Hardware order
Meeting
- Milestone: Hardware order
- Evaluation of milestone objectives:
-
All components except some temperature sensors are ordered.
-
Component placement on PCB is done.
-
The HW development took about 100h instead of the planned 60h which is due to
- elaborate measurement capabilities (RTD and isolated thermocouple)
- case design
- ongoing supply chain shortages (multi changes of microcontroller module and display)
-
The hardware milestone was narrowly missed, which has the following consequences:
- Kernel v0.3.0 will not include any features beyond the ones specified, because some of the SW development time was allocated to HW development.
- No additional measures have to be taken, the other milestones are still on track (mainly because the kernel is ahead of schedule).
-
- Next steps:
- Route remaining nets on PCB.
- Generate PCB design output and order PCB.
- Order temperatures sensors (1x RTD PT100 for in-boiler measurement and 1x K-type thermocouple for in-group head measurement).
- Evaluation of milestone objectives:
| Action Item | Owner | Due Date | Done |
|---|---|---|---|
| Check size fit of PCB from 3D printed parts. | Stefan Lüthi | 17.01.2022 | |
| Order a crimp tool for Molex Micro-Lock PLUS 1.25mm | Stefan Lüthi | 17.01.2022 | |
| Order remaining components and PCB. | Stefan Lüthi | 21.01.2022 |
Next Meeting